Notification of Works
Project Name: A55 Junction 29 to junction 31
Proposed Works: Essential carriageway surfacing repairs, work and soft estate work.
Programme Start Date: Monday 15th November 2021
Programme Completion Date: Friday 3rd December 2021
Client: NMWTRA
USRN: 46804102
Principal Contractor: Hanson Construction Ltd.
I refer to the above and wish to inform you that the works noted will be undertaken between Monday 15th November and Friday 3rd December 2021 at this location.
This could result in a higher than usual level of noise at intervals and I take this opportunity in apologising in advance for any inconvenience incurred.
A full closure of the A55 will be required and will be implemented between 19:30 – 06:00 (when traffic flows are lower).
Follow the Link for full information: A55 Junction 29 to junction 31
